Parcus+ resumed operations at the short-stay car park on 10 June. However, the car park had been closed since 1 May, when a fire broke out.
The safety committee, which met on 23 July, issued a favourable opinion, thereby authorising the reopening of the car park to users.
Throughout this period, the Parcus+ teams worked hard to ensure the site’s safety. The refurbishment work is almost complete: this has included updating the signage, bringing the fire safety system up to standard, painting work, replacing the fire doors and numerous other technical improvements.